Usulan Penjadwalan Perawatan Mesin Filling Secara Preventive Dengan Modularity Design Dan LCC Di PT. Petrosida
DOI:
https://doi.org/10.59581/jkts-widyakarya.v1i2.224Keywords:
Life Cycle Cost, Modularity Design Preventive Maintenance.Abstract
PT. Petrosida is a manufacturing company engaged in pesticide production. The production system in this company is Make To Order (MTO) where the company will produce products after an order or order from consumers. In its production PT. Petrosida has problems with the main tools used for packaging, one of which is a 1-liter induction semi-automatic filling machine in the herbicide unit, where treatment is carried out after damage to a component. Critical components in filling machines experience an average of 20 times damage in 2022-2023 and the machine maintenance process is still not optimal with an average downtime of 5 hours / month. Therefore, the purpose of research is to be able to carry out preventive maintenance using the modularity design method in the hope that there will be no more breakdowns that hamper the production process so as to reduce machine maintenance costs and to find out the minimum total machine maintenance cost planning using the life cycle cost (LCC) method. By implementing preventive maintenance with modularity design, the total maintenance cost of Rp. 9,747,782 is lower than the company's total maintenance cost of Rp. 23,023,176 with an efficiency rate of 42.3%. And obtained the lowest total life cycle cost of Rp. 340,459,348, - with an optimal life on the machine of 3 years & the number of mechanics one person.
References
Ahmad, G. N. (2018). Manajemen Operasi. Jakarta: Bumi Aksara.
Arsyad, M., & Ahmad Z. 2018. Manajemen Perawatan. Yogyakarta : Deepublish.
Badar, M., Endang B., & Judi A. (2018). Analisis Performansi Mesin Menggunakan Metode Reliability, Avaibility, Maintenance (RAM) Analysis dan Penentuan Umur Mesin Serta Maintenance Set Crew Optimal Menggunakan Life Cycle Cost (LCC) Analysis Pada Mesin Dumping Line 1 di PT. XYZ. E-Proceeding of Engineering, 5(2) 2553.
Cahyadi, I. P. (2021). Analisis Reliabilitas, Laju Kerusakan, Dan Analisis Biaya Pada Mesin Penenun Menggunakan Metode LCC di PT XYZ Mojokerto. Jurnal Manajemen Industri dan Teknologi, 2(3) 83-94.
Dzulyadain, H., Endang B., & Fransiskus T.D.A. (2020). Usulan Kebijakan Perawatan Pada Mesin Press di PT XYZ Menggunakan Metode Reliability Centered Maintenance (RCM II) Dan Analisis FMECA. E-Proceeding of Engineering, 7(2), 6528.
Fauziah, S. I. (2019). Analisis Sistem Pemeliharaan Mesin Rajut dengan Metode Preventive dan Breakdown untuk Meminimumkan Biaya Pemeliharaan Mesin Rajut di PT X. Prosiding Manajemen, 5(1), 434-441.
Hani, T. M. (2019). Perhitungan Unit Cost (UC) dan Penyusunan Tarif Rumah Sakit dengan Metode Double Distribution (DD). Yogyakarta: Deepublish.
Irwanto. (2020). Sistem Maintenance Tranformator 60 MVA Pada Electric ARC Furnace (EAF) 7 Slab Steel Plant. Journal of Mechanical Engineering and Mechatronics, 5(2), 75-89.
Muliawati, P. R., Endang B., & Fransiskus T.D.A. (2019). Penentuan Umur Mesin, Estimasi Biaya Dan Maintenance Crew Yang Optimal Pada Mesin Injeksi Plastik Dengan Menggunakan Metode Life Cycle Cost (LCC) Di CV. Gradient. E-Proceeding of Engineering, 6(2), 6460.
Purwantono, Remon L., & Andre K. (2020). Turbin Air Pengantar dan Aplikasinya di Lapangan. Padang: UNP Press.
Putra N. D., Husein H. M. S., & Asngadi. (2019). Analisis Pemeliharaan Mesin Produksi Pada PT. Haycarb Palu Mitra. Jurnal Ilmu Manajemen Universitas Tadulako, 5(1), 61-68.
Putri, N. T., Taufik, & Filly S. B. (2020). Preventive Maintenance Scheduling by Modularity Design Applied to Limestone Crusher Machine. Jurnal Science, 43, 682-687. https://doi.org/10.1016/j.promfg.2020.02.123.
Ritonga, D.A.A. (2019). Penentuan Waktu Prevenive Maintenance Turbin Dengan Metode Criticality Analysis Pada PLTA Sipansihaporas. Jurnal Simetri Rekayasa, 1(2), 58-65.
Rosyidi, R., & Endang P. W. (2020). Usulan Perawatan Preventif Mesin Web Rotary Offset Printing Dengan Menggunakan Metode Modularity Design di PT. XYZ. Jurnal Manajemen Industri dan Teknologi, 1(6), 133-144.
Sulistyo A. B., & Sibro M. (2022). Optimasi Perawatan Mesin Overhead Crane Pada PT. KNS Dengan Metode Reliability Centered Maintenance (RCM) dan Failure Mode And Effect Analysis (FMEA). Jurnal InTent, 5(2), 27-35.
Suwono, A. Z. Z., & Endang P. W. (2020). Penerapan Metode Modularity Design Pada Perawatan Mesin Mixer Secara Preventive Maintenance di PT XYZ. Jurnal Manajemen Industri dan Teknologi, 1(6), 37-48.
Tilammura, F. A., Endang B. & Fransiskus T. D. A. (2019). Analisis Total Biaya Dan Umur Mesin Menggunakan Metode Life Cycle Cost, Analisis Sensitivitas, Dan Analisis Regresi Pada Seluruh Mesin Tower Di PT. Pikiran Rakyat. E-Proceeding of Engineering, 6(2), 6203.
Wijaya A., dkk. (2020). Manajemen Operasi Produksi. Medan: Yayasan Kita Menulis.
Yulius, H., & Freddy T. S. (2020). Usulan Biaya Preventive Maintenance Dengan Menggunakan Metode Modularity Design Pada Mesin Ripple Mill di PT. Incasi Raya POM. Jurnal Sains dan Teknologi, 20(2), 221-227.
Zamani, A. B., & Moch. N., & Said S. D. (2023). Penentuan Interval Penggantian Komponen Mesin Pengayakan Batu Bara Menggunakan Metode Age Replacement. Jurnal Serambi Engineering, VIII(1), 4321-4352.